Timescale box shows AaBbYyZz in Primavera P6
Change color of top columns in Primavera P6
Update the new title field in the Primavera P6 column heading

Primavera P6 Visual Appeal and Formatting
By:  Melanie Calverley


Primavera P6 offers an array of visual features and formatting for its project schedules. Users can benefit from changing bar labels to highlighting areas in the Gantt to enhance the analysis of the project data and timeline. This article addresses several of the useful and popular visual features that you can utilize in your Primavera P6 schedules.

How to Show Text Bar Labels in the Gantt


Sometimes a client wants to see the taskbar labels or text descriptions in the Gantt chart portion of the schedule. The snapshot below shows a Primavera P6 schedule without bar labels:
 













To show the bar labels in a Primavera P6 project schedule, you must adjust the bar settings for the Gantt. First, select the bars icon from the Primavera P6 top menu:
 



Alternatively, you can go to the View tab and select “Bars”:
 








The Bars dialog box will appear. Next, click on the Bar Labels tab and select the “Add” button at the bottom portion of the dialog box:
 














Under the Bar Labels tab, “Position” will default to “Right” and you will leave this as is. You will see options for a pull-down menu under “Label”. Select “Activity Name” from the pull-down menu:
 


















Click “OK”:
 














The Gantt portion of the schedule now shows the taskbar labels. These are identical to the descriptions of each task:












Primavera P6 offers the user several options to customize the project schedule’s appearance. You may prefer to keep Primavera P6’s existing and general field settings; however, if you choose to change the bar styles in the Gantt, select the Bar Style tab of the Bars dialog box first. 

You will see the options to change milestone shapes and alter the colors from a wide selection of a color palette. Ensure that you have the type of task highlighted first (such as a Milestone) and you can make your changes from there by clicking in the color box:
 



















Alter Primavera P6 Column Headings and Update Fonts and Colors in the Project Schedule


Right-click in the column headers or activities and select “Columns…”:
 












In this example, we are going to use the option of “Actual Nonlabor Units” under the Units category, and move it to the right using the arrow to the Selected Options pane. From here, select the button, “Edit Column…”:
 












Update the New Title field to the new column heading. In this example, we will use “Actual NON-LABOR Units”. Next, click “OK”:
 









Notice that Primavera P6 does not alter the original title (in parentheses), as these standard columns maintain the defaults for future projects. Click “OK” once more:
 











The Primavera P6 schedule now shows the new text description in the column:
 






To make changes to the schedule’s font type and size, right-click in Gantt portion of the schedule and select “Timescale…”:
 






Click the button labeled “AaBbYyZz”:
 
















You will see an Edit Font & Color dialog box with the option to change both the font and the color. Select “Font” to change the font type and then click “OK”:
 


















 Changing the font will only change the font of the columns in Primavera P6:
 








You can easily change the font back to the default setting by clicking on the Default Font button in the Timescale dialog box:
 
















Click on the Color button in the Edit Font & Color dialog box to change the color:
 


















 Changing the color will only change the color of the top columns in Primavera P6 as demonstrated in the screenshot below:
 















Modifying Timescale and Calendar Intervals


In the Timescale dialog box, you can also change the date interval. Use the pull-down menu next to “Date Interval” to select a different option:
 















 
You can also put your cursor in the Gantt on the calendar bar and when you get a magnifying glass icon, you can click and drag the calendar columns to stretch out the existing timeline of the schedule view:
 



After stretching the timeline:
 


 
Removing Primavera P6 Relationships from the Baseline Bars


“If you have come across the situation where the relationship lines on your Gantt chart point to the baseline bars, it means that you need to change your Gantt chart options so that you can see the relationship between tasks. When a project is first baselined and progress has been entered, the relationship arrows will connect to the baseline bars instead of the current schedule bars.”

In the screenshot below, you will notice that the baseline bars are all connected between each task and not between the tasks themselves:
 










To change this view, just as before, right-click in the Gantt portion of the schedule and select “Bars…”. By default, the Primary Baseline bar is on top of the order of the other bar options, such as actual, remaining, and critical remaining work bars. Use the Shift down button to move the Primary Baseline bar below all of the other bar options:
 













Click the Apply button and/or “OK” to see the difference:
 














You can see how the relationships re-connected to show the logic arrows between the tasks (blue bars) instead of the baseline (thin yellow bars):









Adding Sight Lines in the Gantt

The example below shows a Gantt without sightlines in Primavera P6:
 












To implement sightlines, right-click in the Gantt and select “Bar Chart Options…”:







Ensure that a checkmark is on the “Show Minor Lines every” box:














Once you click “OK”, you can see dashed lines based on the rows and time options selected from the dialog box:  













Add Curtains in the Gantt Portion of the Primavera P6 Schedule

Primavera P6 allows the user to add “curtains” or shaded areas to enhance certain periods within the Gantt portion of the project schedule. The shaded portion, or curtain, in the Gantt may depict a period in the schedule where the work is on hold or it may designate non-work time in the schedule.

The example below is the Primavera P6 Gantt without a curtain:
 












Right-click in the Gantt and select “Attachments – Curtain – Add Curtain”:
 







Modify the start and finish dates to specify the period for the curtain:
 
















To customize the color and/or pattern of the curtain, click those selections to choose your options:
 














The examples below demonstrate the addition of a curtain with a color option for a designated period:
 























Take note that you can use your cursor on the edge of the curtain in the Gantt to modify the length of the curtain by clicking and dragging the curtain. Primavera P6 also allows the user to create multiple curtains in the Gantt as well.

Conclusion

Primavera P6 users have flexibility in how they present their project schedules. Users and clients can benefit from the visual enhancements that can be added to the Primavera P6 project schedule to assist in analyzation, tracking, and updating of status and project trends.



© 3/22/2021

Original article by author, Melanie Calverley, first posted by Leopard Project Controls at: https://consultleopard.com/primavera-p6-visual-appeal-and-formatting/

Choose timescale from pull-down menu in Primavera P6
Click apply or OK in Primavera P6 for changes
Show Primavera P6 dashed lines in Gantt
Show Primavera P6 logic arrows and yellow bars
Change the font of columns in Primavera P6
stretch Primavera P6 timeline and date columns
Select OK in Primavera P6 bars options
Show primary baseline bar in Primavera P6
Show start and finish dates in Primavera P6 period curtain
Click on color button in Edit Font & Color option in Primavera P6
Primavera P6 can show minor lines every
Show Primavera P6 Gantt curtain
Show the Primavera P6 bar labels


Calverley Consulting LLC Project Management
Right-click Primavera P6 column headers or activities
Choose bar labels tab in Primavera P6 pull-down menu
Change the font back to default in Primavera P6
Show new text description in Primavera P6 column task bars
Primavera P6 bars dialog box
Primavera P6 curtain attachment
Primavera P6 columns options box
Place cursor in Gantt on calendar bar in Primavera P6
Primavera P6 Gantt missing curtain
Right-click Primavera P6 Gantt and select attachments then curtain
Select bar chart options in Primavera P6 Gantt
Go to Primavera P6 View tab and then select bars
Add sightlines in Primavera P6 Gantt
You can customize Primavera P6 curtain pattern and color
Primavera P6 will not alter the original title in parentheses
use timescale dialog box in Primavera P6 to choose date interval
Gantt portion of Primavera P6 bars missing taskbar labels
How to show text bar labels in the Primavera P6 Gantt
This is the title of the web page
Copyright © 2017 - 2023 Melanie Calverley, Calverley Consulting, LLC. All Rights Reserved. This website uses cookies to enhance your browsing experience.
Baseline bars in Primavera P6 Gantt chart view
Edit font and color dialog box to change in Primavera P6
You can use different milestone shapes in Primavera P6
This is the title of the web page